This page provides information about the Transition Process. The Transition Process is governed by Attachment R to BPA’s Open Access Transmission Tariff (OATT).

Applicable Business Practices 

Transition Cluster Study Process 

On March 5, 2025, BPA held a Cluster Scoping Meeting to discuss the Transition Requests received, the proposed grouping of the requests, and next steps for the study process. The meeting materials for the Cluster Scoping Meeting can be found here:

167 Transition Requests were evaluated in the Phase One Cluster Study of the Transition Cluster Study.

Phase One Cluster Study of the Transition Cluster Study

Current Status

The Transition Cluster Study is currently in Phase One. The Phase One Cluster Study, which began on April 19, 2025, was completed January 30, 2026. BPA encourages customers to subscribe to Tech Forum emails to receive updates on stakeholder processes, system changes, and other business-line and agency initiatives, including updates on the status of the Transition Cluster Study: Email Sign-up - Bonneville Power Administration.

  • Study Reports
    • Phase One Cluster Study (links to be added after January 30,2026)
      • SE Idaho (ID1)
      • Lower Columbia 1 (LC1)
      • Lower Columbia 2 (LC2)
      • North Oregon (NO1)
      • South Oregon 1 (SO1)
      • South Oregon 2 (SO2)
      • Tricities/Umatilla 1 (TU1)
      • Tricitis/Umatilla 2 (TU2)
      • Tricities/Umatilla 3 (TU3)
      • West WA (WE1)
      • West OR (WE2)

Important Forms (fillable versions), Templates, and Instructions: