tower"/The Transition Process is the process by which BPA will manage its existing Large Generator Interconnection Queue as it transitions from the existing serial study process to the new cluster study process outlined in TC-25.

Any valid interconnection requests that were submitted by November 22, 2023 may apply to enter the Transition Cluster process.

After June 30, BPA will no longer process individual Feasibility Studies or System Impact Studies for large generator interconnection requests and instead will transition to using a new cluster study process. Customers will have the opportunity to apply for a interconnection request to continue forward into this transition process beginning on June 30, 2024.

Transition Cluster Schedule

  • Event Calendar
  • Transition Business Practice (under construction)
  • OATT TC-25
  • Transition Request Form (Appendix 1) (under construction)
    • Submit Form to Interconnection@bpa.gov
  • Site Control Business Practice (under construction)
  • Commercial Readiness Business Practice (under construction)
  • Cash Payment Instructions
  • Letter of Credit Template - Send to: CRDepositAdmins@bpa.gov
  • Escrow Agreement Instructions and Information contact: CRDepositAdmins@bpa.gov
  • Transition Study Information & Late Stage Facility Costs (under construction)
    • Phase 1 Cluster Study Cost
  • Study Reports (under construction)
  • Technical Interconnection Standards (see Interconnection Page)